Agnes Road / Indian Hill Drive Construction Work Resumes

On Tuesday, 09/19/2017, construction work resumed on Agnes Road and Indian Hill Drive, between Picacho Road (S-24) and Quechan Drive.

Concrete curbs and gutters will be constructed through the beginning of October. Roadbed grading and compaction will also occur. Asphalt paving is scheduled to begin in mid-October. Local traffic will continue to be detoured along Picacho Road (S-24) and Quechan Drive.

The work will bring additional construction equipment and vehicles into the area. Construction work is also continuing on the new Health Care Center.

Please use caution, pay attention to the detour signs, and drive safely around this construction zone.